Capital Projects List

Offices of Facilities Management
0

Capital Projects List

Revised 11/8/2018

No. Building Project Name Funding Source / Management Consultant/Contractor Space Status  /   Phase Start Date End Date Funded Budget Anticipated Project Cost
1 Aaron Davis Hall  Aaron Davis Hall Renovation Reso-A / DASNY THINK Architects Dressing rooms, classroom, office, theaters, roofs and  landscaping Pre-Design  September 2018 May 2019 $6,916,000 TBD
2 Baskerville Hall Baskerville Hall Renovation  DASNY STV Architects / New Style Construction  Lecture hall, new elevator, bathrooms and offices  Construction February 2018 December 2019 $6,460,000 $6,460,000
3 Baskerville Hall Roof Replacement DASNY Superstructure Roof Pre-Design September 2018 September 2019 $2,400,000 TBD
4 Compton- Goethals Roof Replacement DASNY Superstructure Roof Pre-Design September 2018 September 2019 $4,300,000 TBD
5 Fire House Fire House Renovation Reso-A/DASNY Michielli + Wzetzner Architects Gallery, art studios, offices, seminar room, bathrooms and new elevator Design June 2016 October 2020 $10,485,000 $11,000,000
6 Harris Hall  Sophie Davis Interiors (Medical School) Ph. 1 &2 - Additional Installation of FSD DASNY APA Architects/ NSC Construction seminar rooms and offices Substantially Completed September 2018 TBD $800,000 TBD
7 Marshak Hall   HVAC Upgrade, Phase II (Duct risers, part heating conversion)  CUNY-DASNY/CM Gensys Engineering / AKS Contractor Labs and offices spaces  above plaza level Construction June 2017 November 2018 $48,000,000 $48,000,000
8 Marshak Hall   Fire Alarm Upgrade CUNY-DASNY/CM Gensys Engineering / Johnson Controls All spaces   Construction December 2017 December 2018 $2,300,000 $2,300,000
9 Marshak Hall  Mechanical Upgrade - Phase 3A- Lower Level & Emergency Generator CUNY-DASNY/CM Gensys Engineering Lower level spaces and roof Design January 2015 October 2020 $2,445,000 $2,445,000
10 Marshak Hall  HVAC Upgrade- Phase 3B- Central Core CUNY / DASNY Gensys Engineering All interior core spaces Design - On-Hold January 2015 TBD $8,900,000 $8,900,000
11 Marshak Hall  HVAC Upgrade- Phase 3C - Labs (Rm. MR 1113) CUNY / DASNY Gensys Engineering Lab spaces  Design- On- Hold January 2015 TBD $21,100,000 $21,100,000
12 Marshak Hall Biology Teaching Lab Renovation  CUNY / DASNY Graf and Lewent Architects MR 503,504,507 & 511 Design June 2016 April 2018 $2,500,000 $2,500,000
Construction TBD TBD
13 Marshak Hall Modernization of IT Infrastructure Upgrade  Reso-A / DASNY APA Architects Data Closets and MDF Design- On-hold June 2014 December 2018 $6,007,000 $9,000,000
14 Steinman Hall Design August 2018 February 2020
15 Marshak Hall  Plaza Roof & Façade Replacement DASNY APA Architects Exterior Design September 2018 August 2019 $13,500,000 $18,000,000
Bid   August 2019 December 2019
Construction  December 2019 February 2021
16 Marshak Hall Campus Wide Accessibility Project, Phase I DASNY OMNI Architects/Volmar Construction /NSC Construction Lecture Halls & Bathrooms Construction  September 2018 August 2019 $7,253,000 $7,253,000
Shepard Hall  Bathroom Design May 2017 September 2019
NAC  Lecture Halls  Construction Substantially Complete May 2017 August 2018
140th St. bet. Convent Ave. & Amsterdam Ave. Sidewalk  Design May 2017 March 2019
17 Marshak Hall Laser Lab Equipment Replacement DASNY DASNY Procurement  Research Labs Equipment Purchase December 2017 TBD $1,500,000 $1,500,000
18 Marshak Hall  Lecture Hall Upgrade (Seating Replacement) Reso-A / CCNY KI Lecture Hall Furniture Purchase February 2018 April 2019 $1,250,000 $1,250,000
19 Marshak Hall  Pool and locker rooms renovation CUNY / DASNY APA/ Infinity Construction Pool, locker rooms and bathrooms  Construction June 2018 December 2019 $16,414,000 $16,414,000
20 NAC HVAC Upgrade for Library, Tech Ctr, WHCR and Offices   DASNY / CM Dewberry Engineering/ Infinity Construction  Tech Ctr, WHCR radio classroom, Library  Construction  January 2018 April 2019 $9,200,000 $9,200,000
21 NAC Aronow Theater Renovation Reso-A/DASNY Heritage Architects Dressing room, stage, theater, seating Design October 2014 August 2018 $3,200,000 $3,200,000
Construction September 2019 February 2020
22 NAC DSI Equipment Purchase Reso-A / DASNY Multiple AV vendors Library Archive Room Equipment Purchase September 2018 December 2019 $200,000 $200,000
23 NAC, Marshak Hall, Steinman Hall Decommissioning of Existing Fuel Oil Tanks and Installation of New Code Compliant Tanks  DASNY O'Brien & Gere Exterior Design April 2016 March 2019 $950,000 $10,000,000
Construction - On- Hold TBD TBD
24 NAC HVAC Upgrades - Replacement of AHUs NYPA CDM Engineering Mechanical rooms Construction- On-Hold April 2018 December 2019 $19,500,000 $22,500,000
25 NAC Elevator/Escalator - Condition Assessment Study DASNY CSA Group  Elevator and Escalator banks Study March 2017 April 2019 $350,000 $350,000
26 NAC  Exterior Ceiling Replacement DASNY Superstructure Exterior Pre-Design June 2018 March 2019 $338,880 $740,000
27 NAC Culinary Art DASNY TBD Interior Design TBD TBD $300,000 $1,500,010
28 NAC Upper Plaza Waterproofing  DASNY TBD Exterior and Interior Design-Procurement TBD TBD $600,000 TBD
29 Schiff House Daycare Center Renovation Reso-A - CUNY / DASNY Michielli + Wzetzner Architects / Inniss Construction Classrooms, office, bathrooms, kitchen and playground Construction  March 2013 December 2018 $5,000,000 $5,000,000
30 Shepard Hall & IT Upgrade Elevators  Upgrade / Replacement , and IT data closets upgrade CUNY /DASNY - CM Dewberry Engineers / New Style Construction Lobby area on all floors Construction November 2017 October 2020 $9,500,000 $9,500,000
31 Shepard Hall Computer Teaching Lab Upgrade Reso-A/ DASNY Napach Design Group Computer lab and offices  Design February 2016 November 2018 $500,000 $750,000
32 Shepard Hall  Music Library Roof Replacement CUNY / DASNY Superstructure Lower Roof  Complete April 2018 October 2018 $1,000,000 $1,000,000
33 Shepard Hall   Great Hall Interior Renovation DASNY Elemental Architects Auditorium Design March 2018 December 2018 $1,520,000 $1,800,000
34 Spitzer Hall Fabrication Lab DASNY Goshow Architects Fabrication Lab, roof Design September 2017 June 2019 $1,500,000 $1,500,000
35 Spitzer Hall Atrium Roof Reconstruction  DASNY Superstructure Atrium Roof Reconstruction Pre-Design September 2018 TBD $900,000 $900,000
36 Spitzer Hall Harlem Rooftop Garden Reso-A / DASNY Superstructure  Roof Pod Pre-Design November 2017 TBD $201,000 $201,000
37 Steinman Hall Mechanical Upgrade  DASNY Gensys Engineering All spaces Design March 2015 September 2018 $20,546,000 $30,000,000
Construction-On- Hold TBD TBD
38 Steinman Hall Cellar Level Foundation Water Leak & Façade Restoration @ Basement Level, 1M Roof DASNY Superstructure/ SRR Holding Contractor Teaching lab, conference room, offices, plaza and lower roof Construction  March 2018 January 2019 $1,700,000 $1,700,000
39 Steinman Hall Master of Translational Medicine (MTM) Teaching Lab Grove  Foundation/DASNY Transition Design & Architects / Volmar Construction Inc. Teaching lab  Construction Contract phase February 2018 February 2019 $1,500,000 $1,500,000
40 Steinman Hall Zahn Innovation Reso-A Transition Design & Architects  Teaching lab Equipment Purchase September 2017 TBD $500,000 $500,000
41 Wingate Hall Public Safety Locker Room Renovation Reso-A / DASNY Elemental Architects/ Gryphon Construction Inc.  Locker Room, bathrooms, training room Construction October 2018 July 2019 $2,214,000 $2,214,000
42 Wingate Hall Interior Renovation and ADA Upgrades DASNY Elemental Architects Bathrooms, lobby, and new elevator installation Design February 2018 March 2020 $3,000,000 $4,000,000
43 Wingate Hall Lecture Hall Design DASNY TBD Pool In Planning February 2018 November 2018 TBD TBD
$283,899,880 $301,527,010