Capital Projects List

 

City College

           

 

            Phase

Funded Budget

(in thousands)

Anticipated

Project Cost      Anticipated

                     Year of Completion        Notes

Marshak Science Bldg Mechanical Upgrades

Construction

$71,838

$71,838

2023

Phase 1 completed under Project #1283.

(Phase 2 & 3)

 

 

 

 

Phase 2 substantially complete; in

 

 

 

 

 

punchlist and complete Dec. 2019.

 

 

 

 

 

Phase 3A will include em. generator (from

 

 

 

 

 

Project #1287) and fire pump work and will

 

 

 

 

 

be bid Spring 2020.

 

 

 

 

 

Phases 3B & 3C will occur as funding

 

 

 

 

 

allows.

 

 

 

 

 

Phases must occur sequentially.

 

 

 

 

 

Phase 2 project substantially complete and

 

 

 

 

 

turn-over in progress.

NAC Central Plant, Ph 2A  and 2B

Construction

$51,948

$51,948

2022

In construction.  Substantial completion

 

 

 

 

 

anticipated for Winter 2020. NAC Cooling

 

 

 

 

 

Tower portion (phase 2) to follow with

 

 

 

 

 

design & construction started in fall 2019.

 

 

 

 

 

Design is in progress.

NAC Controls Replacement

Construction

$26,000

$26,000

2021

The project will be managed by the New

 

 

 

 

 

York Power Authority. Project in

 

 

 

 

 

construction. CUNY/NYPA have allocated

 

 

 

 

 

additional funds for the College requested

 

 

 

 

 

additional work. Construction kicked-off in

 

 

 

 

 

June 2019 and currently in progress. First

 

 

 

 

 

air handler unit (3rd Fl.) commissioned.

 

 

 

 

 

Substantial Completion scheduled for Jan.

 

 

 

 

 

2021.

Marshak Pool and Locker Room Renovation

Construction

$16,414

$16,414

2020

Construction funding has been added;

 

 

 

 

 

construction in progress. Anticipate

 

 

 

 

 

completion Summer 2020.

Decommissioning Ext. Fuel Tanks

Construction

$16,000

$16,000

2020

Site logistics is being coordinated with the

 

 

 

 

 

College. Design is completed. Construction

 

 

 

 

 

phase kicked off Jan. 2020.

 

 

Steinman/Shepard Elevator

Construction

$12,100

$15,900

2020

Steinman elevators complete and operational. Shepard elevators are in construction. New elevator to be completed by Summer 2020. Upgrade of existing elevator will be complete fall 2020. Building wide IT upgrade (related to elevator work) package is complete and ready for bid.

Additional funding needed will be transferred from Steinman Hall/Marshak Bldg. IT Upgrade project to complete the IT portion of the work.

Daycare Center Renovation

Construction

$9,740

$9,740

2020

Project in construction. Field delays due to installation of new structural elements.

Contractor's non-performance has caused delays - GC has re-mobilized late December 2018 after walking off the site. Construction completion of interior spaces and exterior landscaping is projected to be April 2020. DASNY has hired JOCS Contractor to supplement the General Contractor's workforce. CUNY is working with DoB to set up inspections and expedite filings. Anticipated turnover in April 2020.

 

 

ASRC Interior Renovations

Construction

$9,000

$9,000

2020

1.Ground Floor fMRI Suite/TEM Lab/Low Vibration Lab, Neuroscience 4th Flr, Spectroscopy Lab, and Vivariuim Renovations - Construction completed and occupied. 2. Education Center - Construction complete and occupied. 3.

Photonics Initiative & Low Vibration Lab - Additional funding received from Grad Ctr for Low Vibration Lab, in construction; anticipated completion June 2020; Additional funding for 2 floor Photonics Lab from Grad Center is in progress. Design to start once funding is received.

ALL PROJECTS ARE COMPLETELY FUNDED UNDER ASRC (EXCEPT FOR PHOTONICS SUITES).

Campus-Wide Accessibility Phase 1

Construction

$7,253

$7,253

2020

Due to funding issues and room scheduling, construction has been phased into smaller packages. NAC Lecture Hall interiors complete and occupied. Marshak toilets and lecture halls are substantially

complete. Sidewalk repairs to be done separately in Spring 2020. Construction for Shepard bathrooms will begin Feb. 2020.

Baskerville Hall Interior Renovations and Lecture Hall

Construction

$6,910

$8,700

2020

Construction contract has been awarded, in progress. Construction completion anticipated July 2020. Additional funding required to cover costs of new furniture and on-going field conditions related to existing structure and installation of elevator.

Great Hall Renovation

Construction

$2,300

$2,300

2020

Construction began November 2019 and scheduled to be completed Mar. 2020.

NAC Upper Plaza Waterproofing and Drainage

Construction

$600

$600

2021

Finalizing drawings for bidding. Project awarded to JOCS contractor and construction kick-off will occur 1.22.2020.

 

 
 

Project Count and Sub-Total                12                           $230,103              $235,693

 

Firehouse -MFA Renovation Bid $10,485 $10,485 2022 CUNY-managed project turned over to DASNY for construction. Additional construction funding added. Delay for bidding due to lot separation at NYC Dept. of Finance and NYC DOB (now completed). Final IT systems & equipment selection and specifications complete.  Project is

 
 

currently in bid phase. Construction is projected to start Summer 2020.

 

Shepard Hall Rm 15                                                                                   Bid                                 $800                    $800          2021                                                                                                                       100% design completed and cost estimate

in review. Additional funds have been added to the project for construction. A/V package is being finalized by the Consultant. Project ready for bid. Anticipated construction start Spring 2020.

 
 

Project Count and Sub-Total                  2                              $11,285               $11,285

 

Marshak Plaza and Roof Replacement - Phase 1                              Design                        $21,409               $21,409          2023                                                                                                                    Final construction documents in progress

for Phase 1. FY 20 Crit Maint. funding added to go to bid.

Phase 1 (Plaza, Roof and Stair/Elevator access) proceeding, to be bid in December 2020.

Phase 2 (Facade improvements) on hold for future funding.

60% design on-board review meeting set for Jan 30, 2020 with CCNY, CUNY, &

 
 

DASNY.

 

 

 

Marshak-Hall-Steinman Hall IT Modernization

Design

$6,457

$9,500

2021

Due to funding, college has requested Steinman Hall to proceed as Phase 1 priority. Marshak Hall will follow as Phase 2, as funding becomes available.

90% construction documents in progress. Currently awaiting information from CCNY IT to complete design phase for Steinman Hall only. Funding will be transferred to Shepard Hall IT to fund construction, therefore, design for Steinman Hall IT package will be put on-hold upon completion of construction documents. Project will move to bid once additional funding becomes available.

Wingate Hall Interior Renovation and ADA Upgrade

Design

$5,000

$7,000

2023

Project has completed pre-schematic planning and the consultant has been directed to move onto the Schematic Phase. Design is over budget by approximately $2M. Funding for construction will be added during next CM 2021 funding.

Compton-Goethals Roof Replacement

Design

$4,300

$4,300

2021

Construction document phase (100%) is in review. DASNY will combine construction documents for this project along with the Baskerville Roof Replacement Project and bid as one package. Project will be bid Spring 2020.

Marshak Emergency Generator

Design

$2,445

$2,445

2021

Will be bid as part of Phase 3A HVAC Upgrade Project #1287 for more efficiency in bidding. 100% design documents complete.  Anticipated bid spring 2020.

 

 

Lab Reno 2014 (Marshak 503/504, 507/511)

Design

$2,400

$2,400

2021

100% documents completed. Project is

 

 

 

 

 

being transferred to DASNY for

 

 

 

 

 

construction.  Bidding to occur when

 

 

 

 

 

transfer is complete and package is

 

 

 

 

 

prepped for bid. Consultant design contract

 

 

 

 

 

has been awarded by DASNY. Project will

 

 

 

 

 

resume Feb. 2020 to complete the design

 

 

 

 

 

bid documents.

Baskerville Hall Roof Replacement

Design

$2,400

$2,400

2021

100% construction document phase is in

 

 

 

 

 

review. DASNY will combine construction

 

 

 

 

 

documents for this project along with the

 

 

 

 

 

Compton-Goethals Roof Replacement

 

 

 

 

 

Project and bid as one package. Project will

 

 

 

 

 

be bid Spring 2020.

NAC Escalators & Elevators Study & Phase 1

Design

$2,252

$5,500

2022

Feasibility study accepted by CUNY &

Elevator Upgrade

 

 

 

 

DASNY. Phase 1 project to upgrade

 

 

 

 

 

elevators has now been initiated based on

 

 

 

 

 

Feasibility Study recommendations. Scope

 

 

 

 

 

and funding completed for this Phase;

 

 

 

 

 

design kick-off occurred 10/15/2019.

Spitzer Fabrication Lab

Design

$1,000

$2,200

2021

Schematic report cost estimate is higher

 

 

 

 

 

than available funding. College has removed

 

 

 

 

 

some scope from the project. The

 

 

 

 

 

schematic report and cost estimate will be

 

 

 

 

 

revised and reissued by current consultant,

 

 

 

 

 

in Jan 2020. Design will progress to 90%

 

 

 

 

 

construction documents.

Spitzer Atrium Roof Reconstruction Project

Design

$900

$3,650

2021

Schematic report/design is complete;

 

 

 

 

 

CUNY & CCNY reviewing report. DASNY is

 

 

 

 

 

replacing original consultant with

 

 

 

 

 

Superstructures moving forward into design.

 

 

 

 

 

Design phase is scheduled for kick-off Feb.

 

 

 

 

 

2020, once comments are finalized.

 

 

Aronow Theater Renovation

Design

$767

$5,692

2022

Construction Document completed and in review with CCNY & CUNY. $4.41M City Reso-A funding available for transfer to project to complete construction once design is completed. Project will be bid Spring/Summer 2020 due to college's request to phase the construction of various lecture halls. CP will be submitted July 2020.

Aaron Davis Hall ADA Upgrade and Theater Renovation

Design

$350

$10,000

2023

Consultant procurement completed with DASNY. CP request and Reso A funding transfer will be submitted for construction next year. Design is funded with state dollars, kick-off Sept 2019. Schematic design underway and due March 2020.

NAC Exterior Ceiling Replacement

Design

$339

$1,100

2020

Project set up is complete and design is in progress.

NAC Culinary Art

Design

$300

$1,800

2021

60% CD estimate is higher than available funds. Additional funds needed to complete the design and move to construction.

CCNY & CUNY are re-evaluating scope for possible cuts and additional ResoA funding sources. CCNY, CUNY & DASNY are currently review 60% design documents.

Marshak Reproduction Shop HVAC Study

Design

$200

$200

2020

Study in progress.

 

 
 

Project Count and Sub-Total                15                              $50,519               $79,596

 

Zahn Center Renovation                                                                     Pre-Design $350 $2,200 2021 Design Consultant, Gran Kriegel, is currently preparing their fee proposal for submission and approval. Design is scheduled to begin Spring 2020, once 1184 is approved.

Project Count and Sub-Total                  1                                   $350                 $2,200

 

 

NAC Central Chiller Upgrade                                                                                                        substantially Complete

$33,796

$33,796

2020

Project in Punchlist completion. DASNY is

 

 

 

 

performing and filing final testing.

 

 

 

 

Inspection occurred in November and

 

 

 

 

several deficiencies were identified.

 

 

 

 

Awaiting correction of these items and

 

 

 

 

re-inspection will be scheduled with NYC

 

 

 

 

DOB.

Sophie Davis Interiors (Medical School)                                                                                                        substantially Complete

$14,600

$14,600

2020

Phase 1 completed & occupied. Phase 2

 

 

 

 

complete and occupied. Additional funding

 

 

 

 

provided for replacement of fire smoke

 

 

 

 

dampers within phase 1 and 2 areas, as a

 

 

 

 

change order to the completed work.

 

 

 

 

Fire damper retrofit substantially complete.

 

 

 

 

Additional Day 2 IT upgrade work to begin

 

 

 

 

Spring 2020.

Library WHCR Cooling Syst                                                                                                        substantially Complete

$9,200

$9,200

2019

Construction substantially complete.

ASRC/CDI Retrocommissioning                                                                                                        ubstantially Complete

$3,350

$3,350

2019

Phase 1 work is complete.  Phase 2 is in

 

 

 

 

construction, anticipated completion

 

 

 

 

December 2019.

Wingate Locker Room Project                                                                                                        substantially Complete

$2,214

$2,214

2019

Additional funding has been added to the

 

 

 

 

project for construction. Construction is

Project Count and Sub-Total                                           5

 

$63,160

 

$63,160

 

substantially complete. In punch list.

Project Count and Funding Total     35

$355,417

$391,934

 

 

 

35                               $355,417